Hey Bay: Con Ed preps for more transformer work at the Avenue A substation

Reporting by Stacie Joy

In recent weeks, workers have been doing some prep work at the Con Ed substation on Avenue A between Fifth Street and Sixth Street... work that includes 24/7 security on the scene, moving cones and barriers here and there. 

As of yesterday, the first of the Bay Cranes arrived ... now the work is getting serious. (Emphasis ours.) 

As per workers on the scene, this is a two-week process. First, they will remove and disassemble the old transformer on the Fifth Street side — starting today. This will take a while. (Editorializing.) Then, slated for the weekend after Thanksgiving, the new transformer will go in and provide an Instagram-worthy photo extravaganza. (Try to get a window seat at Sophie's or Somtum Der!)

This is the second transformer replacement at the substation this year... the previous job was a five-month-long project.

Updated 7:37 a.m.

We have liftoff...

1 comment:

  1. Thanks Stacie for the report and pics - don't forget your hard hat for those up close and personal pictures! :)

    ReplyDelete

Your remarks and lively debates are welcome, whether supportive or critical of the views herein. Your articulate, well-informed remarks that are relevant to an article are welcome.

However, commentary that is intended to "flame" or attack, that contains violence, racist comments and potential libel will not be published. Facts are helpful.

If you'd like to make personal attacks and libelous claims against people and businesses, then you may do so on your own social media accounts. Also, comments predicting when a new business will close ("I give it six weeks") will not be approved.