Sunday, January 7, 2024

Photos from new transformer day at the Con Ed substation on Avenue A

Photos and reporting by Stacie Joy 

Yesterday saw the arrival of a new transformer at the Con Ed substation on Avenue A at Fifth Street... the second new one for the facility in the past year

The crews from Con Ed and Bay Crane worked quickly (and efficiently, TBH) to install the 180,000-pound transformer ahead of Winter Storm Ember, which ultimately brought snow flurries and season-appropriate Instagram posts.
The operation included the placement of the new transformer's radiator and cooling tank...
... and here's everything in place and waiting for the hookup...
And based on the street signage on Fifth Street and Avenue B, we look to be in for some more crane work next weekend... (and do they mean Jan. 12 and 13?)...

4 comments:

  1. Awesome coverage.

    ReplyDelete
  2. Great pictures Stacie, wow - and the counter weights on that crane is crazy -

    ReplyDelete
  3. Excellent coverage!

    ReplyDelete
  4. This means no more blackouts, right? Right? Please...

    ReplyDelete

Your remarks and lively debates are welcome, whether supportive or critical of the views herein. Your articulate, well-informed remarks that are relevant to an article are welcome.

However, commentary that is intended to "flame" or attack, that contains violence, racist comments and potential libel will not be published. Facts are helpful.

If you'd like to make personal attacks and libelous claims against people and businesses, then you may do so on your own social media accounts. Also, comments predicting when a new business will close ("I give it six weeks") will not be approved.