Monday, September 23, 2019

What's new below 14th and B?



Here's a street-level look at 14th and B...



Preliminary work started in the summer of 2017 on building new entrances at Avenue A and a new power station at Avenue B.

The weekly L Project newsletter provided an update on what's happening below the streets here ...


[Photo by Trent Reeves/MTA Capital Construction]

Our new substation on 14th Street and Avenue B has floors, walls and a ceiling. That means it's time to start installing the equipment. Here the industrial grade fans arrive, which will help maintain the right temperature in the substation.

The L-train slowdown began on April 26, and is now expected to be finished within a year.

Previously on EV Grieve:
Nightmare scenario for residents who learn that 14th Street and Avenue A will be the main staging area for the L-train reconstruction

2 comments:

  1. Maybe, you know, have a plan to deal with any storm surges so this power plant doesnt blow up like the Con Ed one?

    ReplyDelete
  2. THIS IS A FLOOD ZONE! I live across the street and can tell you this site was totally flooded during Sandy. So typically MTA to put an electric station on a crowded street in a flood zone. State bureaucrat hacks with no clue about how the city works.

    ReplyDelete

Your remarks and lively debates are welcome, whether supportive or critical of the views herein. Your articulate, well-informed remarks that are relevant to an article are welcome.

However, commentary that is intended to "flame" or attack, that contains violence, racist comments and potential libel will not be published. Facts are helpful.

If you'd like to make personal attacks and libelous claims against people and businesses, then you may do so on your own social media accounts. Also, comments predicting when a new business will close ("I give it six weeks") will not be approved.