Tech hub nears halfway mark



Here's another in our periodic looks at the high-profile Zero Irving (aka tech hub) on 14th Street at Irving Place.

Construction here was deemed essential, and work restarting on the site in early May.

According to the 14th @ Irving Construction e-newsletter out this past Friday, work is up to the 10th level of what will be a 21-floor building.

And if you want some super specifics:

The project’s superstructure contractor will complete wall systems cycle for forms on Level 9 (supporting level 10), strip forms on deck below, install rebar in wall forms and close walls starting from East to West. It is anticipated that the East walls will be poured on Wednesday 6/17 and West on Thursday 6/18.

And!

The project’s mechanical, electrical, plumbing and fire protection contractors continue work on site to install sleeves and layout embeds and all other materials being placed into the deck. Stairs and fire standpipes will continue to jump with the building progress, staying (2) floors behind working deck. Plumbing Rough-in work is ongoing on the 2nd and 3rd floors. Fuel oil and storm risers will be installed up through 8th floor. Water risers and duct risers are expected to be up to the 5th floor by 6/26.



The building, developed jointly by the city’s Economic Development Corp. and RAL Development Services, will feature 14 floors of market-rate office space as well as "a technology training center and incubator, co-working spaces, state-of-the-art event space, and street level food hall on the seven floors beneath," per the Zero Irving announcement issued last October.



The new building sits on the former site of a P.C. Richard & Son.

Previously on EV Grieve:
P.C. Richard is gone on 14th Street; preservationists want answers about tech-hub commitments

4 comments:

  1. An upcoming collapse in office space demand is of course the perfect time for the city to be constructing a huge tech hub building

    ReplyDelete
  2. This building is totally **NOT** what de Blah-sio and his cronies claimed it would be, but I'm not surprised given what a deceitful incompetent he'as been from the first minute of his mayoralty.

    ReplyDelete
  3. Wow. Impressive amount of time that this building is half way completed. Just wow.

    ReplyDelete
  4. The demand was questionable before. Now?

    ReplyDelete

Your remarks and lively debates are welcome, whether supportive or critical of the views herein. Your articulate, well-informed remarks that are relevant to an article are welcome.

However, commentary that is intended to "flame" or attack, that contains violence, racist comments and potential libel will not be published. Facts are helpful.

If you'd like to make personal attacks and libelous claims against people and businesses, then you may do so on your own social media accounts. Also, comments predicting when a new business will close ("I give it six weeks") will not be approved.