CB3 committee backs revised Tompkins Square Park recreation plan, with work delayed until 2028

Photos and reporting by Stacie Joy 

The proposed $9.93 million renovation of the Tompkins Square Park recreation area is moving forward again after a Community Board 3 committee voted this past Thursday evening to support a phased approach that would delay construction until 2028. 

The vote by CB3's Parks, Recreation, Waterfront, & Resiliency Committee, held at the BRC Senior Services Center on Delancey Street, followed another contentious, well-attended full Community Board 3 meeting held late last month. 
The project has faced considerable opposition from longtime users of the park's pull-up bars and calisthenics area, many of whom want to preserve the existing equipment and the community that has developed around it.
 
As previously reported, the full Community Board sent the proposal back to committee in late October rather than vote on it, following a heated meeting that drew dozens of residents opposed to the redesign. 

On Thursday, NYC Parks representatives returned with revised presentations, again emphasizing the need to improve accessibility and bring the recreation area into compliance with the Americans with Disabilities Act (ADA).
Parks officials said the Mayor's Office would not allow the city to preserve the existing bars while constructing a separate ADA-compliant workout area elsewhere in the park. They described that approach as creating a "separate but equal" arrangement rather than an integrated, accessible space.
Among those speaking was a Paralympic athlete who uses a wheelchair and emphasized the importance of accessibility.

"I'm not disabled, my environment is," the athlete told attendees. A specialist who works with people with disabilities also addressed the committee.
Committee members discussed several modifications, including retaining the existing backless benches, which park users employ for split squats and other exercises. 

Members also asked whether the park's outdoor pool could serve another purpose during the roughly 10 months of the year when it isn't in use. One suggestion was to temporarily cover the pool to create space for activities such as tai chi. 

A ping-pong table near the fieldhouse will also be relocated to a shaded area near the other tables in the Slocum section of the park. 

Before the vote, most committee members supported Option 2, a phased renovation plan. Option 3, which would exclude the bars from the renovation project (a popular option among attendees), received some consideration but was not discussed in depth. 

The committee ultimately approved a seven-page resolution supporting Option 2, including provisions to retain the backless benches, seek additional community input and postpone construction until the northern section of East River Park reopens across the Sixth Street and 10th Street pedestrian bridges. 

That reopening is currently targeted for late 2027, meaning work at Tompkins Square Park would not begin until 2028. 

Parks representatives said the portion of the project involving the bars could be completed in approximately nine months. They also discussed exploring legally permissible incentives to encourage contractors to finish on or ahead of schedule.
The revised timeline addresses one concern raised by park users: losing access to the outdoor workout area while other recreational facilities remain unavailable during the East River Park reconstruction. 

Still, the meeting made clear that opposition to the redesign remains strong. Several attendees said they felt their concerns were being dismissed and that the committee was not adequately considering their requests to preserve the existing equipment. 

Some also said they felt intimidated or prevented from fully expressing their views. The exchanges became heated at times. Two police officers were present during the meeting, though they were not pressed into service.
The vote prompted further objections from the audience. Afterward, attendees who were not staying for the committee's remaining agenda items were asked to leave.
The recommendation now returns to the full Community Board, which is scheduled to consider the proposal on Nov. 24. (Find a PDF of the Thursday presentation here.)

The broader plan also includes replacing the existing mini-pool with a new in-ground pool (also just for children and their guardians), renovating the basketball courts, replacing fitness equipment and resurfacing the recreation area. 

Previously on EV Grieve: 

No comments: