Wednesday, January 15, 2020

Reminders: Hear the latest on the East River Park reconstruction at this CB3 committee meeting



As a reminder: Tomorrow (Jan. 16) night, CB3's Parks, Recreation, Waterfront, & Resiliency Committee will receive an update on the East River Park rebuild from officials at the Department of Design and Construction.

That committee meeting, which is open to the public, starts at 6:30 p.m. in the BRC Senior Services Center, 30 Delancey St. between Chrystie and Forsyth.

This past Nov. 14, City Council signed off on the hotly contested plan that will bury/elevate East River Park by eight feet as part of the East Side Coastal Resiliency Project. The phased-in construction is expected to begin in the spring. (A coalition of community groups who oppose the plan is expected to file a lawsuit. Read about that here.)

Also as previously reported: There's a petition in circulation to help save the Lower East Side Ecology Center's community compost program. You find the petition at this link.

Photo Saturday by Vinny & O.

Thursday, January 9, 2020

How to help save the Lower East Side Ecology Center's community compost program


[Image via @EastRiverAlliance]

The Lower East Side Ecology Center has launched a petition campaign ahead of the planned reconstruction of East River Park as part of the the hotly contested East Side Coastal Resiliency Project (ESCR) to protect against future storms and rising sea levels.

Per their media advisory:

New York City is currently seeking a construction contract to destroy the East River Compost Yard and create a temporary lawn. The Compost Yard is located in a section of the park scheduled to be reconstructed as part of the ESCR in 2023, but under this recent announcement, the compost yard would be relocated as soon as April 2020.

The alteration of the compost yard into a temporary lawn is moving ahead rapidly without community input and was not announced at recent community board meetings. Not only will this plan cut off New Yorkers from composting and effectively kill our community compost program, but it is also a tremendous waste of taxpayer dollars to create a lawn that will be destroyed in three short years.

There are over 3,500 households donating their food scraps on a weekly basis that participate in this program. We offer 10 drop off locations in Lower Manhattan where we prevent hundreds of tons of organic material from entering landfill every year. The finished compost is distributed for free in the community.

And their ask, per the petition:

If you support composting, please let the City know how you feel. We demand that the Compost Yard stay operational until the 2023 reconstruction for this section of the Park actually starts. We also demand that the City engage with the LES Ecology Center to finish the design for the renovated Compost Yard as part of the ESCR.

The petition is addressed to Mayor de Blasio, Parks Commissioner Mitchell Silver and local City Councilmember Carlina Rivera.

As of this morning, nearly 1,500 people had signed the petition. You can find it at this link.

This past Nov. 14, City Council signed off on the controversial plan that will bury/elevate East River Park by eight feet. The phased-in construction is expected to begin in the spring. (A coalition of community groups who oppose the plan is expected to file a lawsuit. Read about that here.)

Next Thursday (Jan. 16), CB3's Parks, Recreation, Waterfront, & Resiliency Committee will receive an update on the construction and timeline from officials at the Department of Design and Construction. That committee meeting, which is open to the public, starts at 6:30 p.m. in the BRC Senior Services Center, 30 Delancey St. between Chrystie and Forsyth.

Previously on EV Grieve:
• More details on the city's new plan to keep East River park partially open during flood protection construction (Oct. 3)

• At the march and rally to save East River Park (Sept. 21)

• An annual reunion in East River Park (Aug. 4)

• A visit to East River Park (July 10)

Thursday, November 14, 2019

Full City Council vote on resiliency plan for East River Park happens today



City Council is expected to approve the East Side Coastal Resiliency Project (ESCR), the $1.45 billion proposal to protect the East Side from future storms and rising sea levels, with a vote this afternoon. [Updated: They did.]

On Tuesday, the City Council Committee on Land Use signed off on the controversial plan that will bury/elevate East River Park by eight feet.

Also on Tuesday, City Councilmembers Carlina Rivera, Margaret Chin and Keith Powers announced an agreement with the city. You can read the lengthy City Council release here.

The activists behind East River Action were not impressed. They write:

There is little that’s reassuring in it.

For instance, the agreement includes a promise to study the feasibility of protected bike lanes to substitute for the greenway in the park. It will look into “future infrastructural reconstruction” surrounding the FDR Drive.” (Is that about covering the FDR with a park?) It “will conduct further feasibility evaluation to understand whether there is a potential for Interim Flood Protection Measures along the project area.” Once the City Council passes the flood control plan, the city has no obligation to do anything on any of those fronts.

In other headlines about the plan in the last day or two...

• $1.45 Billion Plan To Elevate East River Park Advances, Despite Some Local Opposition (Gothamist)

• How Lower East Side Coastal Plan Braces for Climate Change (The City)

• Opinion: Local City Council Members Must Head Back to Drawing Board on East River Park Plan (Gotham Gazette)

• Opinion: East Side Coastal Resiliency Plan Must Move Forward (CityLimits)

As for what's next, here's The City:

Thursday’s vote only approves land use changes necessary to begin construction on the plan. The final design — which will include specifics about what the new flood walls, park reconstructions and gate system will look like — is expected to go before the Public Design Commission in December, those with knowledge of the plan said.

If all goes as expected, work will commence in East River Park later in 2020.

Previously on EV Grieve:
• Dutch consultant files report on the East Side Coastal Resiliency Project (Oct. 11)

• More details on the city's new plan to keep East River park partially open during flood protection construction (Oct. 3)

• At the march and rally to save East River Park (Sept. 21)

• An annual reunion in East River Park (Aug. 4)

• A visit to East River Park (July 10)

Tuesday, November 12, 2019

With City Council vote looming, NYCHA residents speak out against East Side stormproofing plan


[Along East River Park]

The City Council's final vote on the East Side Coastal Resiliency Project (ESCR), the $1.45 billion proposal to protect the East Side from future storms and rising sea levels, is expected on Thursday afternoon.

Meanwhile, this morning, the City Council Committee on Land Use will weigh in with a vote at 11.

Ahead of these crucial votes, the community pushback continues. Late last week, a group called NYCHA Speaks circulated a letter and petition "to speak out against the lies that are being told at our expense. We are not in favor of the demolition of our park!"

Their letter, sent to local elected officials, states in part:

These petitions are being submitted to you on behalf of nearly 2,000 NYCHA residents of Lillian Wald, Jacob Riis, and Baruch Houses.

These signatures have been collected over the past weeks to show that the vast majority of NYCHA residents do NOT support Option 4 of the ESCR plan. The East River Park has been a vital part of our community for generations, and the demolition of our park will have a devastating impact on the health and stability of our families.

To name just a few of our many concerns:

· The release of contaminants into the air during the demolition and landfill phases. We already suffer a high rate of asthma in our community.

· The negative effects of the loss of much of our local green space (including almost 1,000 mature trees) during the many years of construction. There are thousands of NYCHA families that depend on the East River Park for recreation, school sports, relaxation and family gatherings — in a community that has few alternatives.

Because this plan to demolish and bury the East River Park has received widespread opposition from the community overall, it has been particularly troubling to see how the DDC and City officials have used a very small handful of NYCHA representatives as their “vote of support.”

The staged appearances of these same 2 or 3 individuals in almost every ESCR Town Hall and Public Hearing has slowly created an outrage among NYCHA residents. These individuals are not speaking truthfully for their community! This petitioning effort is a reaction to what we considered was false representation on our behalf.

The Lillian Wald, Jacob Riis, and Baruch Houses suffered the impact of Hurricane Sandy firsthand, and we are aware of the need for flood protection. However, we do not want to sacrifice our park. We see the City’s push to demolish and bury the East River Park as an assault on our history, and on our continued presence in this rapidly gentrifying neighborhood. We understand that construction will need to be done to protect the neighborhood from flooding, but do not support the current plan that the City has chosen.

Last Monday, the City Council Subcommittee on Landmarks, Sitings and Dispositions voted for the plan.

Before the subcommittee vote, Mayor de Blasio announced the formation of a new community advisory group that will provide input on the design and construction progress in East River Park.

No word on who exactly will be part of this "community advisory group."

On Thursday night, officials from the Department of Design & Construction are scheduled to present updates on the plan before Community Board 3's Parks, Recreation, Waterfront & Resiliency Committee. That public meeting is at 6:30 p.m. in the BRC Senior Services Center, 30 Delancey St. between Chrystie and Forsyth.

Previously on EV Grieve:
• Dutch consultant files report on the East Side Coastal Resiliency Project (Oct. 11)

• More details on the city's new plan to keep East River park partially open during flood protection construction (Oct. 3)

• At the march and rally to save East River Park (Sept. 21)

• An annual reunion in East River Park (Aug. 4)

• A visit to East River Park (July 10)

Sunday, October 20, 2019

A full day of activities in East River Park today


[East River Park earlier this week]

Aside from the Tompkins Square Halloween Dog Parade today (Oct. 20) ... there are many activities taking place in East River Park.

This map via East River Action has details (as does this post)...



Among today's highlights: A DRAWathon from 2 to 4 with Rev. Billy and the Church of Stop Shopping...

Per the invite: "There will be supplies, and you can bring some. Draw trees and do some ACTION outreach."



The city's current stormproofing plan for East River Park includes chopping down nearly 1,000 trees.

As Nathan Kensinger's must-read essay on the Park for Curbed points out...:

The environmental impact of the East Side Coastal Resiliency Project would be enormous. In the ESCR’s Final Environmental Impact Statement, which was released in September, the city estimated that their preferred plan would result in the removal of 991 trees, of which 819 are located in East River Park. Many have been growing here since the park opened in 1939, and have root systems too large and complicated to be dug up and relocated. Instead, these trees would be chopped down and replaced with a forest of new saplings planted on top of the landfill. The report estimates that this would eventually result in a gain of 745 trees, but it would take decades for the current tree canopy to fully regrow.

Previously on EV Grieve:
• More details on the city's new plan to keep East River park partially open during flood protection construction (Oct. 3)

• At the march and rally to save East River Park (Sept. 21)

• An annual reunion in East River Park (Aug. 4)

• A visit to East River Park (July 10)

Thursday, October 3, 2019

More details on the city's new plan to keep East River park partially open during flood protection construction



Yesterday came news that the de Blasio administration was announcing more changes to the city's stormproofing plans for East River Park.

As you know, the entire Park was set to be shuttered for three-plus years starting in March. Now, early East Side Coastal Resiliency Project (ESCR) work will commence in the spring, with all of East River Park remaining open until next fall. The flood protection construction will be done in phases.

Here's more via a city press release issued yesterday:

“The community spoke and we listened,” said Mayor de Blasio. “Nearly half of East River Park will remain open throughout construction – without compromising essential flood protections for 110,000 New Yorkers. We are building a more resilient city to meet the challenge of global warming head-on.”

The phasing plan will allow nearly half of East River Park to stay open at all times and will still deliver flood protection by hurricane season 2023, one full hurricane season earlier than under the previous project approach.

In order to enable the new park phasing plan, the schedule for completion of the overall project will be extended to the end of 2025, without any delay in delivering critical flood protection to the 110,000 local residents vulnerable to severe climate impacts in the future. Construction is scheduled to begin in March 2020.

First Phase of Construction (Fall 2020 to Spring 2023): The vast majority of the park areas from Delancey to Houston Streets will remain open as well as the amphitheater area in the south and the portion from approximately East 10th to East 12th Street in the north.

Second Phase of Construction (Spring 2023 to Late 2025): Newly rebuilt portions of East River Park will be open from Houston Street to approximately East 10th Street, as well as the vast majority of the park areas from Corlears Hook Bridge to Delancey Street.

Esplanade areas will follow a separate construction schedule and will be made available as construction permits. To meet the needs of area residents, in addition to phasing, new and improved open space resources will be made available in the surrounding neighborhoods, including a new park adjacent to Pier 42 to be completed in spring 2022.

Details of the plan will be presented at a City Council public hearing this afternoon at 1 p.m. (Oct. 3) in what marks the final stages of the land use review process. (Want to attend? Details here.)

Advocates at the community group East River Park Action, who organized the Sept. 21 rally, were not pleased by yesterday's news. Here's part of their reaction:

This is not good. Our park will still be completely destroyed — just over a longer period of time — five years instead of the original three and a half years.

The city is ignoring the neighborhood’s demands: 1) preserve as much of the park as possible. 2) Construct a resilient coastline — not a massive wall along the river. 3) Construct flood protection along the FDR. 4) Provide interim flood protection during years of construction.

It looks like the whole promenade will be closed while the city builds an 8-10 foot solid flood wall along the river.

The city will say it’s the neighborhood’s fault the timeline is longer because we asked for phased construction. In fact, it’s because they were never going to be able to get it all done in three and a half years, and they knew it.

The project was also undergoing a third-party review by a Dutch consultant hired by Manhattan Borough President Gale Brewer and local City Councilmember Carlina Rivera. No word on this review's status.

Yesterday's changes marked the second time that a significant alteration was announced for the stormproofing project. Last fall, the city surprised community stakeholders by announcing a complete overhaul of a plan that had been discussed over four years of local meetings.

Wednesday, October 2, 2019

Report: City now opts for phased-in approach for stormproofing East River Park


[Photo Sept. 21 by Stacie Joy]

The City will no longer shut down all of East River Park when stormproofing begins in March, opting now for a phased-in approach.

Here's what Gothamist has:

[T]he city has amended its plan to shut down all 45 acres of the park starting this spring, and instead will phase in the construction so only portions of the park are closed to the public at any given time. According to sources familiar with the new plan, the work is expected to be finished in 2025.

The de Blasio administration will announce their change in plans before they have to present them to a City Council land use hearing on Thursday morning, sources tell Gothamist.

We'll post more information as soon as it becomes available. [Updated: Here's the city press release.]

City officials previously planned to close East River Park for three-plus years, elevating it with 8- to 10-feet of soil from Montgomery Street to East 13th Street. Some residents, referring to it as the Kill Our Park Plan, had asked for the demolition and reconstruction of East River Park to take part in phases so that they continue to enjoy some of the amenities that the public space provides... others wanted the original plan that had been in the works for years before the city quietly changed its mind last fall.

Previously on EV Grieve:
• At the march and rally to save East River Park (Sept. 21)

• An annual reunion in East River Park (Aug. 4)

• A visit to East River Park (July 10)

Tuesday, August 27, 2019

Last week to comment on the city's plans to close East River Park


[East River Park photo from Saturday]

Friday (Aug. 30!) is the deadline for public comments on the East Side Coastal Resiliency Project (ESCR).

This link has details on how — and where — to comment.

By now you likely now the story behind the ESCR project, a coastal protection initiative jointly funded by the City of New York and the federal government, aimed at reducing flood risk due to coastal storms and sea-level rise. ESCR is the first element of the city’s "Big U" plan to protect Lower Manhattan from surges like those seen during Superstorm Sandy.

As part of the project, city officials, starting next spring, plan to close East River Park for three-plus years, elevating it with 8- to 10-feet of soil and chopping down trees, etc., from Montgomery Street to East 13th Street.

Some residents, referring to it as the Kill Our Park Plan, have asked for the demolition and reconstruction of East River Park to take part in phases so that they continue to enjoy some of the amenities that the public space provides. (The revised plan, unveiled last fall, dramatically changed course over what had been discussed the previous four years. Community stakeholders said they felt blindsided by the changes.)

For more background:

• The official East Side Coastal Resiliency Project page is at this link.

• "A Beginner’s Guide to the NYC Environmental Impact Statement for the East River Park" via East River Park Action is here.

• A primer on the East River Park's past and future by the Village Preservation is at Off the Grid.

Also, this Gothamist piece has a nice background of what has transpired to date.

You may also breeze through the mostly unreadable Draft Environmental Impact Statement for the project here. There are hundreds and hundreds of pages of documents with footnotes and collateral materials (the table of contents alone is a unwieldy 32 pages).

The final vote via City Council is expected in late September.

And tonight (Aug. 27), the East River Park Action group is hosting a meeting at the Sixth Street Community Center between Avenue B and Avenue C (more details here) ...




Previously on EV Grieve:
Report: The reality of storm-proofing East River Park in 2020

Storm center: Questions linger over updated plans for the East Side Coastal Resiliency project

At East River Park

Friday, July 19, 2019

Next steps in the plan to rebuild East River Park



On Wednesday night, Manhattan Borough President Gale Brewer hosted a public hearing at Mt. Sinai Beth Israel on the East Side Coastal Resiliency Project, and the city's updated (as of last fall) plans to stormproof East River Park from Montgomery Street to 13th Street.

Under the current plan, now on tour through the city’s Uniform Land Use Review Procedure (ULURP), East River Park will close from March 2020 to (fingers crossed) summer 2023.

Aside from what city officials say will reduce flooding from coastal storms and the rise of sea level on the East Side, the all-new East River Park — elevated by eight feet — would include new amenities.



You can read about what transpired at the meeting via Gothamist ... and Curbed.

An excerpt from Gothamist:

“Whatever the park is giving us, you’re going to take it all away,” said Yvette Mercedes, a Baruch Houses resident, whose children play in the park. “We need fixing, but why do it all at once?”

Over 25 people testified at the hearing, and expressed their anger at how City agencies — the Department of Design and Construction, and the Department of Parks and Recreation — are handling the project.

The complete park closure, and health hazards brought on by the dumping of landfill are the two most contentious points among residents and city officials. Residents have also pled with city officials for a “greener” plan that is not only flood-safe, but environmentally friendly.

And Curbed:

Though Manhattan Borough President Gale Brewer called for a two-month delay on the project’s Uniform Land Use Review Procedure, the Department of Design and Construction (DDC) first deputy commissioner Jamie Torres Springer said at the hearing that only the DEIS comment period will be extended for two weeks.

Ian Michaels, a spokesperson for the DDC said that the comment period for the DEIS, which has been open since April, will now be extended until Aug. 30.

Next up: The City Planning Commission hearing on July 31 at 10 a.m., at 120 Broadway. The final vote via City Council is expected in late September.

Meanwhile, City Limits took a deep dive on the issue leading up to Tuesday's meeting. It's a good primer for what has happened to date. Read that here.

An excerpt:

Charles Krezell, the co-founder and president of LUNGS (Loisaida United Neighborhood Gardens), was in disbelief last fall when he heard about the city’s new plan. “No one was prepared for it,” he says.

He is unsure that this project can be completed in just three years and worried that it will stretch beyond the current terms of elected officials who will approve it, diffusing accountability. “No one else [in city office now] is going to be in office at that point, so it’s going to be very difficult, the city can walk away, the city can run out of money, anything can happen,” he says. “We can have a flood tomorrow, there’s no barrier to protect us from anything.”

Previously on EV Grieve:
At East River Park

RIP East River Park

Tuesday, June 11, 2019

Reminders: This week's meeting lineup on stormproofing plans for East River Park



As a reminder, here are your opportunities this week to learn more about the East Side Coastal Resiliency Project as the public review process continues:

• ULURP Public Hearing – Parks, Recreation, Waterfront & Resiliency Committee
Tuesday, June 11, 6:30 p.m.
PS/MS 188 – The Island School, 442 E. Houston St. (entrance at Houston/Baruch Drive)

• CB6 Full Board Meeting
Wednesday, June 12, 7 p.m., 433 First Ave. between 25th Street and 26th Street (NYU School of Dentistry), Room 210

• CB3 Parks, Recreation, Waterfront & Resiliency Committee Meeting
Thursday, June 13, 6:30 p.m., Henry Street Settlement Youth Services Gymnasium, 301 Henry St. (CB3 posted several relevant documents on the project here ahead of the meeting.)

Last fall, the city unveiled an updated plan, which took residents, community leaders and local-elected officials by surprise after years of outreach and groundwork. The revamped plan — released without any community input — is radically different than what had been discussed. City officials have said in various presentations that this approach will provide a reduced construction time, resulting in an operable flood protection system for the 2023 hurricane season and future sea rise.

Creating the intricate flood protection system would see the city close East River Park for up to three and a half years starting in March 2020.

Also, the Draft Environmental Impact Statement is available for public comment until Aug. 15. Find those details on how to comment here.

Previously on EV Grieve:
Here are the next meetings for you to learn more about stormproofing plans for East River Park

Monday, June 3, 2019

Here are the next meetings for you to learn more about stormproofing plans for East River Park



Now's your chance to hear more from various city agencies and officials about the plans to stormproof the East Side of Manhattan (aka the East Side Coastal Resiliency Project).



Here's a list of upcoming meetings...

Community Open Houses
• Wednesday, June 5, 4-8 p.m.

and

• Thursday, June 6, 2-8 p.m.

Peter Cooper Village, 360 First Ave., lower level (entrance on the east side at 21st Street).

ULURP Public Hearing – Parks, Recreation, Waterfront & Resiliency Committee
Tuesday, June 11, 6:30 p.m.
PS/MS 188 – The Island School, 442 E. Houston St. (entrance at Houston/Baruch Drive)

CB6 Full Board Meeting
Wednesday, June 12, 7 p.m., 433 First Ave. between 25th Street and 26th Street (NYU School of Dentistry), Room 210

As previously reported, to stormproof the East Side and protect residents from storms the magnitude of Sandy, the city plans to "lift" East River Park by up to 10 feet when work starts in March 2020.

Creating the intricate flood protection system would see the city close East River Park for up to three and a half years, shutting down the current amenities, cutting down many of the trees and rebuilding the newly renovated running track, among other things.

The draft environmental impact statement — 900-plus pages — for the East Side Coastal Resiliency project is currently available for review and comment. My previous post here has more details on the review process and links to relevant materials.

Last fall, the city unveiled an updated plan, which took residents, community leaders and local-elected officials by surprise after years of outreach and groundwork. The revamped plan — released without any community input — is radically different than what had been discussed, and its expected cost will increase from $760 million to $1.45 billion. City officials have said in various presentations that this approach will provide a reduced construction time, resulting in an operable flood protection system for the 2023 hurricane season.

Meanwhile, community coalition group East River Alliance has a petition in circulation calling for a change to the plans.

Monday, May 13, 2019

3 chances to hear about the city's plan to stormproof East River Park — and the East Side


[Photo of East River Park from last week]

You have several chances this week to learn more about the city's plans to stormproof the East Side of Manhattan ...



Per the invite via the city's Department of Design and Construction (DDC):

Please stop by to learn more about current plans for flood protection along Manhattan’s Lower East Side and planned park improvements. City agencies and members of the design team will be available to explain and answer questions about the design, the associated Uniform Land Use Review Procedure (ULURP) application, and the project’s Draft Environmental Impact Statement (DEIS). Community members are encouraged to drop in to the Open House at their convenience.

Community Open Houses
• Tuesday, May 14
4-8 p.m.

• Wednesday, May 15
2-8 p.m.

Both info sessions are at the Lower Eastside Girls Club, 402 E. Eighth St. at Avenue D.

And on Thursday, DDC reps will make a presentation before CB3's Parks, Recreation, Waterfront, & Resiliency Committee at 6:30 p.m. That public meeting is at the BRC Senior Services Center, 30 Delancey St. between Chrystie and Forsyth.

As previously reported, to stormproof the East Side and protect residents from storms the magnitude of Sandy, the city plans to "lift" East River Park by up to 10 feet when work starts in March 2020.

Creating the intricate flood protection system would see the city close East River Park for up to three and a half years, shutting down the current amenities, cutting down many of the trees and rebuilding the newly renovated running track, among other things.

The draft environmental impact statement — 900-plus pages — for the East Side Coastal Resiliency project is currently available for review and comment. My previous post here has more details on the review process and links to relevant materials.

Last fall, the city unveiled an updated plan, which took residents, community leaders and local-elected officials by surprise after years of outreach and groundwork. The revamped plan — released without any community input — is radically different than what had been discussed, and its expected cost will increase from $760 million to $1.45 billion. City officials have said in various presentations that this approach will provide a reduced construction time, resulting in an operable flood protection system for the 2023 hurricane season.

Meanwhile, community coalition group East River Alliance has a petition in circulation calling for a change to the plans.

Per the petition:

East River Park is the largest park in Manhattan below 59th Street and a precious recreation space for a community where many residents cannot afford vacations.

There will be no access to a 3-mile stretch of waterfront from 23rd Street to Montgomery Street. No ball games, barbecues, sprinklers and playgrounds, runners, bikes, walkers — for nearly four years.

We demand that the City reconsider this plan. Our community deserves a resiliency plan that includes:
• Flood protection now and during construction
• Phased closing during construction and immediate reopening of completed sections
• Real alternatives for healthy recreation during construction
• Consideration of other options including flood protection along the FDR and covering the highway to create additional parkland

Find the petition here.

Tuesday, January 22, 2019

Reminders: City Council's oversight hearing on the revised East River Park stormproofing is tomorrow



Tomorrow afternoon at 1, City Council is holding a joint committee hearing with de Blasio administration officials and relevant agency commissioners about the updated East Side Coastal Resiliency Project. (Find the agenda item at this link.)

Council members — led by District 2's Carlina Rivera — hope to learn more about the city's new vision for the revamp to stormproof East River Park. The updated plan was released in the fall, in an L-train-ish fashion that caught many stakeholders by surprise after years of outreach and groundwork.

The updated plan — released without any community input — is radically different than what had been discussed, and its expected cost will increase from $760 million to $1.45 billion, while closing and burying the current East River Park for up to three-plus years. (The city's new design renderings are at this link.)

The Times caught up to the story in a piece headlined To Save East River Park, the City Intends to Bury It on Sunday.

An excerpt from the Times:

In a separate interview, the Parks Department commissioner, Mitchell J. Silver, said that unlike passive parks that double as floodplains, like those by Jamaica Bay, East River Park has structures, lights and synthetic turf, which “does not do well” in floods. And with the river projected to rise two and a half feet in 30 years, raising the park is the only way to save it.

By bringing in landfill and soil by barge, the new plan allows for daytime construction away from the highway, minimizing traffic disruptions. After its scheduled March 2020 launch, the new plan can thus be completed in three years rather than five, with flood protection in place by 2022.

Still, the park’s closing under either plan has left people like Joan Reinmuth, a retired nurse and 30-year East Village resident, doubtful. “This park is more than a recreation facility,” she said. “These kids in NYCHA houses don’t take vacation cruises. They don’t shop at Zabar’s for fish; they fish to eat. Early mornings, men are shaving in the fountains.”

Rivera, who called for Wednesday's oversight hearing, shared her thoughts on the project in series of tweets on Friday...




Previously on EV Grieve:
Report: The reality of storm-proofing East River Park in 2020

Storm center: Questions linger over updated plans for the East Side Coastal Resiliency project

Mayor's new East River Park flood plan faces City Council scrutiny

Wednesday, January 9, 2019

Mayor's new East River Park flood plan faces City Council scrutiny



On Jan. 23, City Council is holding a hearing with de Blasio administration officials about the updated East Side Coastal Resiliency Project. (Find the agenda item at this link.)

As you know, the Mayor's office announced a new vision for the long-delayed revamp to stormproof East River Park back in the fall. The updated plan is radically different than what had been discussed, and its expected cost will increase from $760 million to $1.45 billion, while closing and gutting the current East River Park for up to three and a half years. (The city's new design renderings are at this link.)

City Councilmember Carlina Rivera, whose district is most impacted by the new plans, announced the joint hearing of the City Council’s Committees on Parks and Environmental Protection yesterday.

Here's part of her statement:

"This hearing will finally give the Council and our community the chance to hear directly from the Mayor’s team and relevant agency commissioners regarding the recent changes to this monumental coastal protection project. Even with multiple community briefings and meetings with elected officials, we still do not have important details about this project, and I expect the Mayor’s team to come well prepared and help us understand the need for these drastic changes.

This new plan represents a fundamental departure from anything the City has previously discussed and would reportedly bring the projected cost of the project to $1.45 billion. The Mayor’s Office has failed to provide detailed analyses for explaining why this $700 million increase is necessary.

In addition, this new plan would require the closure of East River Park, the only real green space for tens of thousands of NYCHA residents and community members on the Lower East Side, for three years. Officials have not explained in any way how they will provide alternate outdoor space for this community, which has one of the highest asthma rates in the city.

We want a resilient city, and we will use this hearing to ensure that this project and others like it throughout the city can actually accomplish our progressive environmental goals."

The previous stormproofing as part of the East Side Coastal Resiliency Plan would have required closing a lane of the FDR and working around Con Edison power lines. However, city officials have said that building out the flood protection and reconstructing the park would eliminate these FDR traffic issues as well as speed up the construction process by one hurricane season.

In addition, the most recent version of the plan would transform the East River Park into a "world-class park" with a variety of courts for tennis and basketball and (fields for soccer) — all protected from storms and sea-level rise.

Meanwhile, tomorrow night, CB3's Parks, Recreation, Waterfront, & Resiliency Committee will hear updates on the East Side Coastal Resiliency project. The committee meeting starts at 6:30. Location: BRC Senior Services Center, 30 Delancey St. between Chrystie and Forsyth.


[Proposed schedule via the city. Click to go big.]

Previously on EV Grieve:
Report: The reality of storm-proofing East River Park in 2020

Storm center: Questions linger over updated plans for the East Side Coastal Resiliency project

Wednesday, December 26, 2018

Storm center: Questions linger over updated plans for the East Side Coastal Resiliency project



The folks at LUNGS (Loisaida United Neighborhood Gardens) are spreading the word — as seen in the holiday-themed flyers above — about the city's new plans to storm-proof East River Park.

Details emerged earlier this fall (city press release here) about the updated construction phase to protect the East Side against catastrophic flooding along the East River from Montgomery Street to 25th Street. (Most of the changes occur between Cherry Street and 13th Street.)

As reported in October, the-now $1.45 billion project raises East River Park by up to 10 feet when work starts in March 2020. To do this, though, the city will need to close East River Park for up to three and a half years, bulldozing all the current amenities, including the new running track and soccer field.

The previous storm-proofing as part of the East Side Coastal Resiliency Plan would have required closing a lane of the FDR and working around Con Edison power lines. However, city officials have said that building out the flood protection and reconstructing the park on top would eliminate these issues as well as speed up the construction process by one hurricane season.

The city's two public meetings earlier this month on the East Side Coastal Resiliency Project apparently didn't do much to educate the public on its revised plans or provide adequate time for feedback.

Per the LUNGS website:

Very complicated plans were presented for 45 minutes and the public was asked to respond for 30 minutes and fill out stick ’ems to be put on printed drafts and proposed construction diagrams. That was the extent of the public involvement. There has been no transparency in this process.

The Villager and Town & Village have recaps from these meetings.

Per The Villager:

[I]t took the city four years to realize the pitfalls of the previous plan, to the chagrin of locals and Downtown politicians, who have several unanswered questions.

“Part of the problem is the city can’t answer basic questions about why this is necessary and what range of options they’ve considered to protect this community for resiliency,” said state Senator Brian Kavanagh. Kavanagh sent a joint letter with nine other Manhattan pols to the Mayor’s Office last week outlining their concerns.

“On some level, the proposal here today is to destroy this park in order to save it,” Kavanagh said. “And if we could be persuaded that this is the only way to protect the community from catastrophic storms, that would be a good start to this conversation, but unfortunately this city, after many years of planning, decided without consultation to scrap the original plan and announce an entirely new plan.”

At the meetings, the city released new design renderings of the revised resiliency plan. (You can find the 57-page PDF of the new plan at this link.)

Here is a rendering showing the finalized area around Delancey, including a new pedestrian overpass...



... and a look at areas between Sixth Street and 10th Street...



According to The Villager, the new resiliency plan could begins its months-long Uniform Land Use Review Procedure as early as this coming spring ... with construction starting in March 2020 and lasting through the fall of 2023.

On the flyers posted at neighborhood community gardens, LUNGS is encouraging residents to submit feedback on the new plan. You may submit comments to the city via this link. LUNGS has more ways for residents to get involved at this link.

Previously on EV Grieve:
Report: The reality of storm-proofing East River Park in 2020

Sunday, December 9, 2018

[Updated] 2 chances to hear updates on the East Side Coastal Resiliency Project this week



City officials are hosting two community meetings this coming week to discuss updated plans for storm-proofing East River Park.

Details emerged earlier this fall about the construction phase to protect the East Side against catastrophic flooding along the East River from Montgomery Street to 25th Street.

As reported in October, the city plans to "lift" East River Park by up to 10 feet when work starts in March 2020. However, to do this, the city will need to close East River Park for up to three and a half years, bulldozing all the current amenities, including the new running track and soccer field.

Monday's meeting is from 7-8:30 p.m. at the Gouverneur Health Auditorium, 227 Madison St. Tuesday's meeting is 6:30-8 p.m. in the Hunter-Brookdale Rotunda, 425 E. 25th St. (And the flyer notes dinner will be served!) The flyer notes that the same material will be presented each night (not sure if the same dinner will be served each night).

This link takes you to the website for the East Side Coastal Resiliency Project ... where you can find various background reports and presentations.

Updated 12/10

Ahead of tonight's first meeting, local City Councilmember Carlina Rivera released this statement:

“After being briefed last week on the new design for the East Side Coastal Resiliency Project, I am still seriously concerned that many important questions regarding this monumental project have not been sufficiently answered by the Mayor’s Office and that the community’s pain-staking work over four years is being completely pushed aside. This new plan represents a fundamental departure from anything the City had previously discussed, particularly with respect to East River Park, which would be closed for three years.

Moreover, the proposed changes would reportedly bring the projected cost of the project to $1.45 billion, which the Mayor’s Office has failed to provide detailed analyses for explaining why the cost increase is necessary. We want a resilient city, and this projects needs to demonstrate that that is possible in all Five Boroughs. If the Mayor can clearly show that the previous, community-led version of ESCR would not provide the sufficient coastal protections needed, the city needs to be forthcoming about that. If they are pursuing this version out of convenience for the drivers who use the FDR or because they are concerned about finishing the project on time, they should also detail that as well. But until these questions are answered, I cannot back the direction the Mayor’s Office has decided to take.”

Previously on EV Grieve:
Report: The reality of storm-proofing East River Park in 2020

Monday, October 5, 2015

Last chance for input on the East Side Coastal Resiliency Project


[Image via]

There are two remaining design presentations and outreach sessions this week regarding the East Side Coastal Resiliency Project.

Officials will be presenting actual design alternatives that residents can provide feedback on the project, which is being designed to mitigate future climate change and flood risks along the East River.

Here's the official description of the project:

The East Side Coastal Resiliency Project is a federally funded coastal protection initiative aimed at reducing flood risk due to coastal storms and sea level rise on Manhattan's East Side from East 23rd Street to Montgomery Street.

The ESCR Project is a priority of the City of New York as outlined in the 2015 One New York: The Plan for a Strong and Just City and by the innovative Rebuild by Design competition sponsored by the U.S. Department of Housing and Urban Development (HUD). The project design intends to integrate flood protection into the community fabric, improving access to the waterfront rather than walling off the neighborhood.

As a CB3 rep told us:

"If folks are interested in providing feedback on what the waterfront will look like for the foreseeable future, then they should attend one of these two sessions ... these sessions are the opportunity for the public to weigh in on actual design alternatives. The waterfront will never look the same again, and people deserve a right to weigh in on that decision-making process."

Presentation locations:

Tuesday, Oct. 6
5:30-7:30PM
Grand St. Settlement
80 Pitt St.

Thursday, Oct. 8
6:30-8:30PM
Washington Irving High School
40 Irving Place