Full CB3 to vote on phased Tompkins Square Park recreation overhaul tonight

The full Community Board 3 will vote this evening on a revised plan for the $9.93 million reconstruction of the Tompkins Square Park mini-pool, basketball courts and adult fitness area. 

CB3's Parks, Recreation, Waterfront & Resiliency Committee voted on Nov. 12 to support Option 2, which would complete the project in two phases rather than close all three recreational areas simultaneously.

Under the proposal, the pool, basketball courts and 10th Street entrance would be reconstructed first, with the existing calisthenics area remaining open and accessible from the Ninth Street side of the park. That initial phase is expected to take approximately 15 months. 

Once the pool and courts reopen, the fitness area would close for an estimated nine months for reconstruction. The committee is asking Parks to shorten that closure if possible and coordinate with the East River Park reconstruction team to ensure replacement outdoor fitness facilities are available before the Tompkins area closes. 

The project includes replacing the deteriorating mini-pool with a larger, accessible in-ground pool that would double capacity from approximately 33 to 66 swimmers. The pool would continue to serve children and their guardians.

Plans also call for reconstructed basketball courts, additional practice basketball opportunities, improved accessibility, taller fencing, drainage repairs and new landscaping. 

The resolution includes several requests addressing concerns raised by regular park users, particularly those who use the longtime calisthenics equipment. Parks has measured and scanned the existing structures and committed to reproducing their principal exercise functions and characteristics. The committee also wants durable replacement equipment and backless benches suitable for traditional exercises.

However, the committee rejected Option 3, which would have left the existing fitness area largely intact, arguing that it would not adequately address accessibility and other improvements.

The committee also wants Parks to provide updates on the materials selected for the replacement exercise equipment and any significant changes to the construction schedule. 

The $9.93 million project includes $6.1 million from New York State's NY SWIMS program and $3.83 million in city funding. Construction is expected to begin in 2028 — after the northern section of East River Park reopens. 

Separately, the resolution calls for additional funding to repair deteriorating pathways throughout Tompkins Square Park, including the pothole-filled Ninth Street transverse. Parks previously identified about $1.1 million in available funding, compared with an estimated $2.2 million needed for pathway repairs. 

Tonight's vote follows several months of community discussions and design revisions. The full board previously returned the proposal to committee after Parks presented changes at its Oct. 27 meeting. 