[What lies beneath East Houston]
Anytime that you've tried to cross East Houston from Avenue A west to the Bowery these past, oh, six years, you've probably wondered, When, dear [____], will this construction ever end?
To answer that very broadly — sometime this year. Probably!
Various reps for the never-ending East Houston Reconstruction Project appeared before CB3's Transportation & Public Safety/Environment Committee on Tuesday night. BoweryBoogie was there and learned that — ding! ding! — there will likely be another delay in completing the project.
Per BoweryBoogie:
Not only is the project delayed three years, but the September 2016 completion date previously provided was stretched again by another month. If you’re keeping score at home, that’s easily the third revised end date in recent memory. Blame more of the “utility interference” that contractors encounter each time the roadway is torn asunder (i.e. encountering issues with different agency wiring that needs attention).
Oh, and here are some photos of the Greenstreets pedestrian plaza outside Punjabi Deli from the fall... the work was finished around that time, but the final planting inside of the planters and bench installation likely won't happen now until the fall...
As, as previously posted, here's how the new Greenstreets and street configurations at Avenue A and Houston will look ...
And here are some general highlights from the city's latest East Houston Street Reconstruction Project newsletter (PDF!):
Proposed Work Schedule Winter 2016
1.Continue excavating and install 36” trunk water main at the Bowery and East Houston Street
2.Continue excavating and install trunk water main on East Houston Street between 2nd Avenue and the Bowery
3.Continue installing new catch basin and chute connection at 2nd Avenue
4.Begin excavating and install new center median planters
The DDC is reconstructing/replacing combined sewers, trunk main, water mains, catch basins, fire hydrants, sidewalks, etc., etc., along East Houston Street, from the Bowery to the FDR Drive. This work phase started in June 2010, when the Lakers beat the Celtics to win their 16th NBA Championship and "Jonah Hex" was playing in theaters.
Previously on EV Grieve:
Coming soon to East Houston: Construction, hell, rodent control stations
Long-threatened East Houston reconstruction starting this month
East Houston Street construction will be a living hell for an extra year
How you can help Punjabi Grocery & Deli stay in business
Never-ending construction continues to hurt Punjabi Grocery & Deli
Taxi Relief Stand arrives on Avenue A; Punjabi Grocery & Deli relieved