Here's what is turning out to be a monthly look at 124 E. 14th St., aka Zero Irving (and formerly the Union Square Tech Training Center and 14 @ Irving ... and tech hub for life!) ... workers are apparently up to the tippy top here at Irving Place...
The latest Zero Irving e-newsletter (14th @ Irving Construction Update #36, and, by the way, #2 is already a collector's item) states the following updates:
Superstructure Concrete
The project’s superstructure contractor will be completing the 23rd floor slab the week of 9/7. They will continue to place stairs at the top of house, in addition to mechanical pads, curbs and the buildings parapets. Upon completion of this miscellaneous concrete the contractor will begin demobilization. This will include cocoon removal, removal of shoring and decking material and other demobilization tasks.
Cellar
The project’s electrical contractor is finishing installation of Switchgear Room equipment and feeder conduits in coordination with Con Ed’s site visits. End line boxes will be completed, along with overhead conduits throughout the cellar. Con Ed is anticipated to complete their pulls and tie-ins to switch gear room. The project is expecting permanent power by October 2020.
General Site
The project’s mechanical, electrical, plumbing and fire protection contractors continue work on site to install sleeves and layout embeds and all other materials being placed into the deck on the 23rd floor.
The new building — long contested by local preservationists and community groups (see links below) — sits on the former site of a P.C. Richard & Son on city-owned property.
Previously on EV Grieve:
• Behold Civic Hall, the high-tech future of Union Square — and NYC
• Speaking out against a 'Silicon Alley' in this neighborhood
• City Council unanimously approves tech hub; some disappointment in lack of zoning protections
• The conversation continues on the now-approved tech hub for 14th Street
• P.C. Richard is gone on 14th Street; preservationists want answers about tech-hub commitments