Big crane steels the spotlight on 1st Avenue
Large crane action to note today... this work is happening over at 75 First Ave. between Fourth Street and Fifth Street, where an 8-floor, 22-unit condoplex is in the works next door to the Rite Aid.
Workers are putting steel beams in place...
After nearly 14 months of inactivity here, worked picked up again this spring. As such, the completion date on the plywood rendering has been adjusted to summer 2020.
This slowly-developing development broke ground in September 2016.